Data centers
Nokia Kolmenkulma Data Center Site
Kolmenkulma Data Center Site is ideally located at the heart of the logistical Center of South Finland, near the city of Tampere approximately 17 km away. National road network connects the area with four major harbors at the West and South coast of Finland. Capitol city of Helsinki is less than two hours away with a motor way and also flight connection making it convenient to fly all the way to Tampere-Pirkkala via Helsinki-Vantaa or Stockholm airports. Site area is approximately 13,4 hectares. Area can be built fast to house a Data Center. Power and water connections are available due to existing industrial zoning in the area. Finland has a very stable geological environment due to oldest bedrock of the world. There are no flood risks or other disaster risks from the nature. The area is one of the key ICT areas in Finland with strong academic institutions and innovative spirit. Continuous ongoing investments to house new technology and industries will provide customers that would put the DC waste heat into good use. The area will have significant investments supporting circular economy and material re-circulation. Companies producing bio gas from organic waste, companies that recycle plastics and rubber and also turn plastics and rubber into oil through pyrolysis are just a few examples of such companies.
Zoning readiness
Zoning ready for data center useNotes on investment regulatory readiness
?
Building right / [m2]
53 548Site area / [m2]
133 870Easements
No easements
Notes on site size and building permit
The area reserved for DC at this stage is approximately 13.4 hectares. There´s however more area available at the Kolmenkulma business area that could be used for DC extension when needed.
Building right can be extended when needed. No definitive max value.
Design rules and regulations
EU and national regulations. Exceptions can be approved by officials when proven feasible and filling the required guidelines.
Pre-approval of construction and environment permits, fire and rescue plan
Negotiations not startedSite shape
Site area is close to been rectangular area.
Notes on site topography
Site is quite flat with trees largely removed. It´s easy to clear any other remaining vegetation and level the ground to required elevation.
Prevailing wind directions
Prevailing wind direction is South
Listed per centage between different compass points:
N 9%, NE 8%, E 6%, SE 12%, S 17%, SW 16%, W 11%, NW 9%
Natural water source available for cooling
AvailableIf yes, distance to water source / [meters]
2 500Notes on cooling options
Cooling options of the site are excellent. Both air and water cooling options are possible. The climate gives efficient air cooling option around the year and there´s plenty of surface water reservoirs in the vicinity to provide make-up water for for the cooling towers.
Type of ground
Fairly even soil surface, some forestry and other surface vegetation.
Levelling of plot
Plot is partly construction ready / levelledType of forestry (if plot not levelled)
Typical tree types in the area are bruce and pine.
Layout plan of datacenter building(s)
Preliminary plan exitsExisting buildings
No existing buildings
Existing power systems
No existing power systems.
Notes on existing infrastructure
The site is a part of a 850 hectare industrial area that will be hosting a wide variety of cleantech, ICT and recycling companies.
Natural risks
No natural risks in the area
Proximity of major roads, airports, flight paths and railways
Railway station 5 km
To highway 1 km
Port of Helsinki 190 km
Tampere-Pirkkala airport 14 km
Hki-Vantaa Intl. airport 185 km
Tampere downtown 13 km
Turku 160 km
Port of Rauma 140 km
Port of Pori 120 km
Proximity of hazardous industries
No hazardous industries close by
Proximity of near by communities
Site is located approximately 5 km from the center of the Nokia city and approximately 17 km from the center of the city of Tampere.
Current access to the site
Two or more roadsNotes on current and planned access to the site
Current roads are changeable in case needed in the design.
Emergency vehicle accessibility
Accessibility is fast and easy with the motorway close by
Distance to nearest international airport / [km]
185Distance to nearest fire & rescue station / [km]
11Distance to nearest police station / [km]
6Distance to nearest hospital or health care center / [km]
6Availability of public transportation
Bus stop within walking distance. Train station at the centre of Nokia approximately 6 km from the site.
What is needed to realize total power supply?
Infrastructure uppgrade needed:
New 110 kV switchyard, new 110 kV line, uppgrade at Melo 110 kV substation
Lead time for total power supply to the site / [months]
72Redundancy power availability
Available (same as total main power feed)Arrangement of redundancy power
Infrastructure upgrade needed switchyard at DC:
- New 110 kV line
- 110 kV switchyard extension
- 110/20 kV power trafos
Infrastructure upgrade needed substation in MELO:
- New 400/110 kV switchyard
- New 400/110 kV power trafo
Distance to 10 kv power connection point / [km]
1Distance to 20 kv power connection point / [km]
1Distance to 110 kv power connection point / [km]
1Distance to redundancy power connection point / [km]
1Distance to local grid substation, 110 kv / [km]
10Distance to national grid substation, 400 kv / 110 kv / [km]
10First phase electricity power supply (in 18 months or sooner)
4-6 MWFirst phase power supply to the site
0 - 18 monthsFirst phase electrical feed to the site
20 kVFirst phase redundancy power availability
Available (same as first phase main power feed)Notes on power supply
Power supply can be increased over 100 MW with uppgrading the infrastructure if the need should rise.
Local green energy
AvailableDetails on local green energy (suppliers)
Nokianvirran Energia
Leppäkosken Sähkö
Tampereen Sähkölaitos
Local electricity supplier(s)
Tampereen Energia Oy
Leppäkosken Sähkö Oy
Nokianvirran Energia Oy
Distance to optical fiber infrastructure / [km]
0.2Distance to optical fiber infrastructure / [miles]
0.124274Amount of diverse connections
3 or moreConnectivity supplier(s) to provide diverse connectivity
FNE Finland Oy
Teknomeria
Elisa Oyj
DNA Oyj
Arrangement of connection diversity
On planned DC area, there´s Elisa, TeliaSonera and Tampereen Puhelin
Elisa, TeliaSonera, Cinia, Teknomeria, FNE and DNA with backbone connection to Nokia.
Dark fiber on the site
AvailableLead time for minimum of two connections / [months]
4Distances to local internet exchange points (ix) in Finland
TREX in Tampere City Center approximately 15 kmDescribe different cable routes from the site to key directions in and from Finland
Direct route to Europe
- Nokia – Tampere buried next to railway
- Tampere – Helsinki buried next to road number 130
- Helsinki – Rostock via C-Lion1
- Rostock – Frankfurt via Gas line fiber route
- RTD estimation 22ms
Route via Sweden to Europe
- Nokia – Tampere buried next to railway
- Tampere – Helsinki buried next to road number 130
- Helsinki – Rostock via C-Lion1
- Rostock – Frankfurt via Gas line fiber route
- RTD estimation 22ms
Routes to Russia
- Nokia – Tampere – Jyväskylä – Pieksämäki – Mikkeli next to railway
- Mikkeli – Ylikkälä – Vyburg OPGW route
- Nokia – Tampere next to road
- Tampere – Lahti – Kouvola next to road number 12
- Kouvola - Lappeenranta next to road number 6
- RTD estimation to Moscow 12,7 ms
Commitment of local utility companies
Ongoing planning and investment readiness existsWater utilities on site
Potable water supply availableNotes on water utilities
Water utilities will be installed during 2017
District heating network
AvailableNotes on district heating network
The site will be connected with the district heating system in the near future.
Natural gas availability on site
Not availableNotes on (liquid) natural gas
?
Opportunities to utilize waste heat
The waste heat could be used for the companies that are already at the area and the ones that will establish themselves later. This would be very suitable since the area is developed to house in cleantech companies.
Distance to delivery point / [km]
1Investment incentives
?
Other cost benefits
?
Availability of skilled laborforce
There´s plenty of skilled labor available, both mechanical and electric expertice.
Close by is Tampere that has a very strong engineering education culture - both technician and engineer level.
Higher education resources
Tampere University of Applied sciences
Tampere Technical University of Science
University of Tampere
Tampere Polytechnic
Tampere Vocational College
Person(s) responsible for provided information
Reijo Parkkinen (Project Manager)