Data centers
Kotka, Mussalo Data Center Campus (reserved until 04/2024)
- Kotka - Hamina region has a strong experience with Data Centers - Google is already here.
- Mussalo is an excellent place for a modern and an efficient data center at the harbor. Strong local commitment for innovative solutions.
- Heating network for Kotka City Center next to the site – possibility for very cost efficient energy and heat re-use
- Site area is area is 26 hectares.
- 3 km from center of Kotka, at Mussalo Harbor operated by Port of HaminaKotka Ltd = good logistics
- Permitted building volume approx. 100,000 m2 – and scalable.
- Distance to waterfront 400 meters.
- Competitive solution for power and power transmission. Scalable up to 200 MW.
- Water and air cooling options.
- Multiple backbone data network lines along motorway E18. The site is well connected on main fiber networks to the Russia and Europe.
Zoning readiness
Zoning ready for data center useNotes on investment regulatory readiness
Owner levels the plot. Ready for construction in three months. Site is not on groundwater area. City authorities are willing to co-operate with site planning and permitting.
Building right / [m2]
100 000Building right can be extended up to / [m2]
150 000Site area / [m2]
260 000Site area can be extended up to / [m2]
300 000Easements
None
Notes on site size and building permit
Building Permit can granted in short handling period.
Pre-approval of construction and environment permits, fire and rescue plan
Plans pre-approved by all authoritiesNotes on site topography
The Campus site is flat, solid rock and at least +5 m above sea level (minimum recommendation in the area is +3,14 m). The second image is the elevation model in Mussalo (from NLS, National Land Survey of Finland). DC site area has been excavated after the current elevation model laser scan was completed.
Prevailing wind directions
Prevailing wind is SW, which is typical on the shores of Gulf of Finland.
Natural water source available for cooling
AvailableIf yes, distance to water source / [meters]
400Notes on cooling options
Several different cooling options:
- Direct air cooling
- Ambient air conditions favor direct air cooling
- With adiabatic cooling white space temperature does not exceed 25 °C
- Cooling towers
- High stability due to low ambient wet bulb temperature
- Makeup water available from several sources
- Sea water cooling
- Very high stability and efficiency
- Cost-effective especially in larger scale
Detailed plans for all cooling options available.
Type of ground
Solid rock / moraine. Plot will be leveled by the owner (City of Kotka).
Levelling of plot
Plot is partly construction ready / levelledLayout plan of datacenter building(s)
Preliminary plan exitsNatural risks
No danger for flooding.
- A publication by Finnish Meteorological Institute; “Long-term flooding risks and recommendations for minimum building elevations on the Finnish coast”, June 2014. The minimum recommended building elevations are based on the sea level in 2100 with an exceedance frequency of one event per 250 years. Minimum recommended building elevation without wave compensation in Mussalo is 314 cm above sea level (calculated by linear interpolation from Helsinki and Hamina mareograph data).The estimated minimum plot level will be + 500 cm above sea level.
Finland has solid ground, no natural disasters
Southern Finland locates in very peacuful area concerning earthquakes. There have been some earthquakes also in Kotka - Hamina area as everywhere else on earth, but their size have been small and duration very short. Local earthquakes are part of earthquake serie where Eurasian tectonic plate pushes under other tectonic plate. Due to the fact that there have been only minor earthquakes, they are not needed to take account in any building regulations or orders. (Source: University of Helsinki, Institute of Seismology)
Proximity of major roads, airports, flight paths and railways
Nearest highway (E18): 6 km - E18 motorway is a 4-lane connection to Helsinki (75 min)
Nearest major international airport: Helsinki airport 130 kilometers, 1 hour 15 minutes by car
Other connections: International harbor next to the site, train stations and central bus station in close range (3 km)
Main roads to Kouvola (40 min) and Lappeenranta (90 min).
Proximity of near by communities
Nearest community: City of Kotka (+ 50 000 people) - City Centre in 3 km. Connections & logical driving routes are not going trough the city center. Practically no traffic jams.
Current access to the site
Two or more roadsNotes on current and planned access to the site
Easily accessed by two alternative routes: via Merituulentie or via Mussalontie.
Emergency vehicle accessibility
Kotka City Rescue department within 6 km (7 min).
Kymenlaakso Central Hospital within 4 km (5 min).
Two alternative routes to the site.
Distance to nearest international airport / [km]
130Distance to nearest fire & rescue station / [km]
6Distance to nearest police station / [km]
3Distance to nearest hospital or health care center / [km]
4Availability of public transportation
Several bus routes go through next to the site.
What is needed to realize total power supply?
New 110 kV overhead line between Kymi 400/110 kV and Pernoonkoski 110 kV substations 8 km (Fingrid). 110 kV switchyard extension and transformers at DC site.
- Electricity system investment depends on the security of supply required by the client, but quick start up with 15 MW of power use is available within 6 months.
Lead time for total power supply to the site / [months]
12Redundancy power availability
Available (same as total main power feed)Arrangement of redundancy power
Two separate lines from Kymi via Pernoonkoski. 15 MW redundant 20 kV supply from Hovinsaari and Hanskinmaa substations within 6 months.
Distance to 110 kv power connection point / [km]
1Distance to redundancy power connection point / [km]
1Distance to local grid substation, 110 kv / [km]
1Distance to national grid substation, 400 kv / 110 kv / [km]
8First phase electricity power supply (in 18 months or sooner)
11-20 MWFirst phase power supply to the site
0 - 18 monthsFirst phase electrical feed to the site
20 kVFirst phase redundancy power availability
Available (same as first phase main power feed)Local green energy
AvailableDetails on local green energy (suppliers)
9 windpower mills within the area (1 - 20 km) ~10 MW.
A solarpower plant within the area (20 km) ~1 MW.
2 hydropower plants within the area (30 km)
All Nordpool (common electricity market within the Nordics) green energy options available.
Local electricity supplier(s)
Kotkan Energia Oy
Kymenlaakson Sähkö Oy
Amount of diverse connections
3 or moreConnectivity supplier(s) to provide diverse connectivity
FNE Finland Oy
Elisa Oyj
Dark fiber on the site
AvailableLead time for minimum of two connections / [months]
3Distances to local internet exchange points (ix) in Finland
125Describe different cable routes from the site to key directions in and from Finland
At least four 5 different diverse fiber routes are available:
- via road number 170 to Loviisa – Porvoo – Helsinki
- via Anjalankoski – Elimäki – Orimattila – Mäntsälä – Kerava
- via sea cable
- Via Kouvola – Lahti – Mäntsälä – Helsinki
- Via road number E18 Kotka – Helsinki
From Helsinki
- via sea cable to Rostock - Frankfurt - etc
- via sea cable to Stockholm
- via sea cable to Tallin
A new Sea cable to Kotka (Mussalo harbor / 1 km) from Rostock via Baltics and Helsinki is planned to be ready by the end of 2018
Commitment of local utility companies
Ongoing planning and investment readiness existsWater utilities on site
Potable water supply availableDistrict heating network
AvailableNotes on district heating network
District heating next to the site. Local energy company (Kotka Energy) ready to negotiate of excess heat usage and solutions - plans already available.
Natural gas availability on site
Natural gas availableNotes on (liquid) natural gas
Possibility to also build an LNG terminal next to the site.
Opportunities to utilize waste heat
District heating of City of Kotka. Network next to the site. Additional possibilities also discussed (Closed circuit fish farming, greenhouses, etc.).
Investment incentives
Terms for a long term plot lease are negotiable.
Other cost benefits
Kotka Energy ready to discus the solution for excess heat to compensate the energy cost for the site. Very substantial benefit + sustainable solution for DC campus.
Notes on local ecosystem
The local ecosystem has been built since 2009 when Google decided to set one of its biggest Data Centers in Europe to Kotka-Hamina area.
- Strong local experience and excellent network of companies in Data Center business
- The strongest possible energy grid
- The best connections to both West and East
- Continuous development with Universities and other Educational institutes
- Strong local commitment – with cities and other authorities
Availability of skilled laborforce
Very good experience already in the area. All Helsinki workforce within close range. Also good connections to both Aalto University (Helsinki area) and Lappeenranta Unviersity (within 90 km). EKAMI (local community college) has already established courses for DC operators. XAMK (local University for Applied Sciences) also ready to start a program specialized in DC planning / operations.
Person(s) responsible for provided information
Janne Korkeamäki (FDI Executive)